Stage 1 demolition has been completed in the living and family room entry areas. The family room entry was extended and squared off for alignment with the French door removal. Kitchen cabinets, appliances, the island, and the drop ceiling were removed, with flooring scraped and drywall work underway. Family room windows, a small door, and interior openings to the laundry room were removed and are being closed up; stretch rock sheets are being used for a cleaner finish. In one of the two front bedrooms, shutters, drop ceilings, and doors were removed, and the interior door to the family room is being closed off while maintaining the main entrance access. Stretch rock installation has begun. Living room demolition included removing shutters, rotting paneling, and the drop ceiling. The non-operational fireplace and a second bedroom door were enclosed with drywall to accommodate an electric fireplace insert and built-in shelving. The master bedroom saw the removal of carpet, the drop ceiling, built-in cabinets, shutters, and drapes, with closet cleaning completed. In the master bath, demolition was completed, including removing two entry doors, the sink mirror, and the tub. Framing and drywalling are underway for a double vanity, and a jetted tub has been prepped for installation. The third bedroom is fully demoed and ready for drywall this week, with the fireplace closed off and under consideration for either an electric insert or drywalling. In the first front bedroom, demolition is complete, and framing/drywall work has started on the second entry door and fireplace.